The plumbing is dry fitted and I went around touching up electrical. Work day was 7:30 till about 3. HUMID! It was definitely humid. Now back to the paying job for a few days. Actually back to the bill paying job. I am saving over half a year salary by doing the plumbing and electrical myself, so this is the actual paying job. 🙂
-Michael

Drywall

Michael,   Just a quick update on my meeting with Eduardo, the sheetrock contractor, and his drywall hanger, Victor:   It will be more efficient for them to wait until all the plumbing, electrical, and carpentry punch-out items (pocket door in master, stairwell, garage furr-down) are complete, rather than bringing in their crew in stops and starts.  If their path is clear, they can have all the drywall installed in 2-3 days.  Tape, float, and texture will take about just as long, depending on humidity levels (drying time between coats).   I will see what I can do this week about finishing the remaining carpentry items.   Let me know if you have any questions.   Thanks, Jeff