This is the plan of attack once we get the green light.
• Foundation pad – excavation and fill
• Foundation – forming, pouring and finishing the slab. This would include any below-slab plumbing and electrical (kitchen island) rough.
• ICF walls (any through-wall rough-in for electrical, plumbing, and HVAC needs to be completed before concrete is poured)
• Interior wall framing
• Ceiling/attic framing & decking
• Roof framing & decking (roofing can be installed immediately afterward or can be scheduled for later. I would, at a minimum, have the roofer install the roofing membrane at this time).
• Exterior Windows & Doors installed (stucco can begin once this is completed)
• Wiring
• Plumbing rough-in
• HVAC rough-in
• Spray foam insulation
• Drywall
• Interior doors and/or trim
• Plumbing set-out (toilets, tubs, etc)
• Lighting installed
• HVAC trim-out
• Cabinets
• Interior Paint
• Tile
Category: New House
Documentary of building the house
Floor tiles
Counter in bath
Tile
We found a deal on some marble flooring. Checking to see if it is a pain in the ass or not before purchase.
Time line
OK, here is the house timeline.
keep in mind that this is the worst case. I think.
Bank status.
The appraisal will be 2-3 weeks.
The title will be 2-3 weeks.
Building status.
Excavation 2 weeks
Foundation 2 weeks
Wall erection 2 week)s
Interior wall erection 2 weeks
Plumbing 2 weeks
Electrical 2weeks
Doors n windows 1 week
Roof n gutters 2 weeks
Drywall 3 weeks
Exterior 2 weeks
Cabinets and floor 2 weeks
Not sure what it adds up to, but it should be no later than May 1st.
Much longer than we thought! Partly because we can not get in until it is completely completed.