I decided to come in and stop for the day. I should be done this weekend or next and 9 hour days of work on my days off will now be the limit! I have a work plan that looks like this.
finish copper water in plumbing
pressure test then find and fix leaks.
Finish the electrical meter that had to be redone.
Finish the 2 inch water line (repair).
Finish the electrical in the house.
By this point the drywall should be started if not already done.
Cabinets should be in place.
Install the appliances.
Move in!!!
Contract the counter tops installation.
Prime all the drywall
Paint all the ceilings
Paint the rooms and set the fixtures in place
Cover the floors.
of course this order is subject to change. 🙂